Predictability

Reports

Overview

The Predictability tab answers the question: how reliably does this team deliver what it commits to, and how long will it take to finish the backlog? It combines commitment reliability history, scope creep analysis, and a Monte Carlo simulation to give data-driven delivery forecasts at different confidence levels.

KPI cards

CardWhat it shows
Commit ReliabilityAverage percentage of committed story points delivered on time. Green ≥ 80%, amber 60–79%, red < 60%.
Avg Scope CreepAverage percentage of unplanned work injected into sprints relative to original commitment. ≤ 10% is acceptable.
P50 ForecastMonte Carlo result: 50% of simulated runs complete the remaining backlog within this many sprints.
P85 ForecastMonte Carlo result: 85% of simulated runs complete within this many sprints. Recommended date to commit to stakeholders.

Remaining backlog slider

Above the Monte Carlo chart there is a slider labelled Remaining backlog. Drag it to adjust the number of story points remaining (10–500). The simulation recalculates immediately — use this to run "what if" scenarios: if we descope 50 points, when do we finish? Click Reset to return to the actual backlog figure from the project.

Charts

ChartHow to read it
Monte Carlo Completion ForecastRuns 10,000 sprint simulations using historical throughput to estimate how many more sprints are needed to finish the remaining backlog. The histogram shows the distribution of simulation outcomes. The cumulative probability line (blue) rises from left to right — read off any sprint number to see the probability of finishing by then. P50 (green), P85 (amber), and P95 (red) confidence lines are marked.
Commitment Reliability per SprintBar chart showing the reliability percentage (accepted ÷ committed × 100) for each sprint. Colour-coded per bar: green ≥ 80%, amber 60–79%, red < 60%. A dashed trend line and an 80% target line are overlaid.
Scope Creep AnalysisDual-axis chart. Bars show the raw injected story points per sprint. The red line shows scope creep as a percentage of the original commitment. ≤ 10% is acceptable; 10–20% is a watch signal; > 20% is at risk.
Predictability charts
Monte Carlo forecast histogram with P50, P85, and P95 confidence lines
Use P85 as your commitment date with stakeholders — it means there is an 85% chance of finishing by that sprint. P50 is an optimistic target; P95 is a conservative safe date.

Troubleshooting

The Monte Carlo chart is empty

The simulation requires at least 3 sprints with completed story points. Complete more sprints to enable the forecast.

The P85 forecast shows a very large number of sprints

The forecast is based on historical throughput. Low average velocity combined with a large remaining backlog will produce a long forecast. Use the remaining backlog slider to test different scenarios.

I adjusted the backlog slider but the forecast didn't change

The forecast recalculates automatically when you drag the slider. If the chart doesn't update, try refreshing the page — the slider state may have desynchronised.

Commitment Reliability shows 100% for some sprints but the team clearly missed work

Reliability is calculated as accepted ÷ committed. If stories were carried over without being un-committed from the sprint, the committed figure stays the same and reliability will be overstated. Ensure unfinished stories are removed from the sprint before closing.